Nerdy, sourced Starship tracking at every site

Claimstrip

06:14 CST at Starbase

Launch pad board

Pads

4 launch sites, each built only from ledger claims. Components are the pad hardware sources name, with the place the ledger keeps and any newer competing claim beside it. Activity is every claim about the pad or its hardware, newest first. Flights list sourced NETs; a NET is not a liftoff. Each pad also draws a ground-systems timeline from those claims. Nothing here is inferred.

Starbase

Starbase Pad 1 P1

Launch pad, being rebuilt

Ground systems

One mark per claim whose effect at is this pad, or whose about names hardware the ledger places here. The earliest word in the summary picks the lane. Words that start together keep the longer one. A summary with none of them is Other. Filled marks are confirmed. Hollow marks are unconfirmed, and the table keeps the UNCONFIRMED stamp.

Starbase Pad 1 ground systems, 6 Sept to 10 NovLaunch mount / legsChopsticks / towerDeluge / water tanksBQD / SQDFlame deflectorTank farm / propellantOther6 Sept13 Sept20 Sept27 Sept4 Oct11 Oct18 Oct25 Oct1 Nov8 Nov2026-09-06 Chopsticks / tower: Reported 6 Sep 2026: the weather tower on Tower 1 was removed that week so the protective roof could be lifted onto the tower.2026-09-13 Chopsticks / tower: Reported 13 Sep 2026: Pad 1 tower had its roof reinstalled early in the week of 7 Sep, after it was taken down for modifications.2026-10-11 Flame deflector: Pad 1 flame deflector under construction in the Sanchez lot; TrackingTheSB says work on it continued steadily through the week of 5 Oct.2026-10-15 Chopsticks / tower UNCONFIRMED: Pad 1 tower base received walling work while the first Launch Mount leg was being lifted into position.2026-10-15 Launch mount / legs UNCONFIRMED: The first of the new Pad 1 orbital launch mount legs was installed into the flame trench.2026-10-16 Flame deflector UNCONFIRMED: The flame trench apex support beam was lowered into the Pad 1 trench.2026-10-16 Flame deflector UNCONFIRMED: Teams at Pad 1 lifted a piece of the flame bucket into place as the pad rebuild takes shape.2026-10-16 Other UNCONFIRMED: A new piece of drawworks balcony wall was set in place at Pad 1.2026-10-18 Flame deflector: TrackingTheSB weekly: this week teams lifted the centre flame bucket part into the Pad 1 trench and began installing the launch mount legs. The last flight from Pad 1 was Flight 11.2026-10-18 Launch mount / legs UNCONFIRMED: The crane Littler Larry was lifting the second new orbital launch mount leg into position at Pad 1, in breezy conditions.2026-10-21 Launch mount / legs UNCONFIRMED: The Littler Larry crane lifted the third launch mount leg into place at Pad 1.2026-10-22 Launch mount / legs UNCONFIRMED: The fourth launch mount leg was lifted into position at Pad 1.2026-10-23 Flame deflector: Another section of flame trench wall was lifted into place at Pad 1.2026-10-25 Launch mount / legs UNCONFIRMED: TrackingTheSB weekly: this week the four legs that hold the orbital launch mount were installed at Pad 1 over a couple of days.2026-10-27 Flame deflector UNCONFIRMED: Work on the Pad 1 flame trench continues.2026-10-30 Deluge / water tanks UNCONFIRMED: NSF reports the top deck deluge plates were lifted onto the Pad 1 launch mount during the week of Flight 15 static fires.2026-11-02 Other UNCONFIRMED: The dead-line spool for the Pad 1 drawworks reached the launch site, driving through the D1 gate toward the pad.2026-11-10 Flame deflector: The second of four sloped wall sections was installed in the Pad 1 flame trench, and VickiCocks15 later saw another sloped trench wall section lifted into place.
DateLaneSummaryClaim
2026-09-06Chopsticks / towerReported 6 Sep 2026: the weather tower on Tower 1 was removed that week so the protective roof could be lifted onto the tower.c-0e735138eefc
2026-09-13Chopsticks / towerReported 13 Sep 2026: Pad 1 tower had its roof reinstalled early in the week of 7 Sep, after it was taken down for modifications.c-8adbfedefc93
2026-10-11Flame deflectorPad 1 flame deflector under construction in the Sanchez lot; TrackingTheSB says work on it continued steadily through the week of 5 Oct.c-20437032bb02
2026-10-15Chopsticks / towerPad 1 tower base received walling work while the first Launch Mount leg was being lifted into position.c-2aa04b79217c UNCONFIRMED
2026-10-15Launch mount / legsThe first of the new Pad 1 orbital launch mount legs was installed into the flame trench.c-c61dd0c20c22 UNCONFIRMED
2026-10-16Flame deflectorThe flame trench apex support beam was lowered into the Pad 1 trench.c-7baeefce1da2 UNCONFIRMED
2026-10-16Flame deflectorTeams at Pad 1 lifted a piece of the flame bucket into place as the pad rebuild takes shape.c-b0b10ab55b94 UNCONFIRMED
2026-10-16OtherA new piece of drawworks balcony wall was set in place at Pad 1.c-cd927e9de285 UNCONFIRMED
2026-10-18Flame deflectorTrackingTheSB weekly: this week teams lifted the centre flame bucket part into the Pad 1 trench and began installing the launch mount legs. The last flight from Pad 1 was Flight 11.c-315c655dbad4
2026-10-18Launch mount / legsThe crane Littler Larry was lifting the second new orbital launch mount leg into position at Pad 1, in breezy conditions.c-8266d2703d91 UNCONFIRMED
2026-10-21Launch mount / legsThe Littler Larry crane lifted the third launch mount leg into place at Pad 1.c-3d0e41a7c0af UNCONFIRMED
2026-10-22Launch mount / legsThe fourth launch mount leg was lifted into position at Pad 1.c-e7e7b3cd27af UNCONFIRMED
2026-10-23Flame deflectorAnother section of flame trench wall was lifted into place at Pad 1.c-fe5eef2d2c97
2026-10-25Launch mount / legsTrackingTheSB weekly: this week the four legs that hold the orbital launch mount were installed at Pad 1 over a couple of days.c-c74779406712 UNCONFIRMED
2026-10-27Flame deflectorWork on the Pad 1 flame trench continues.c-326d880b23fb UNCONFIRMED
2026-10-30Deluge / water tanksNSF reports the top deck deluge plates were lifted onto the Pad 1 launch mount during the week of Flight 15 static fires.c-2a1a1ddab0fe UNCONFIRMED
2026-11-02OtherThe dead-line spool for the Pad 1 drawworks reached the launch site, driving through the D1 gate toward the pad.c-109fd456e3bc UNCONFIRMED
2026-11-10Flame deflectorThe second of four sloped wall sections was installed in the Pad 1 flame trench, and VickiCocks15 later saw another sloped trench wall section lifted into place.c-e5a6ffc5303f
Launch mount / legs
orbital launch mount, launch mount, mount legs, mount leg, olm
Chopsticks / tower
chopsticks, chopstick, towers, tower
Deluge / water tanks
deluge, water tanks, water tank
BQD / SQD
quick disconnects, quick disconnect, quick-disconnects, quick-disconnect, bqds, bqd, sqds, sqd
Flame deflector
flame deflector, deflector, flame trench, flame bucket
Tank farm / propellant
tank farm, propellant
Other
no word from the lanes above

Components

3 pieces from the hardware register. Now at is the last confirmed place a source stated, or an unconfirmed place stamped as such when nothing confirms one. A newer unconfirmed place sits beside it as a candidate.

  1. Pad 1 flame deflector (rebuild) pad1-flame-deflector

    Now at Starbase Pad 1.

    2026-10-18 CONFIRMED note at P1 about pad1-flame-deflector c-315c655dbad4

    TrackingTheSB weekly: this week teams lifted the centre flame bucket part into the Pad 1 trench and began installing the launch mount legs. The last flight from Pad 1 was Flight 11.

    @TrackingTheSB X post Confirms alone

  2. Pad 1 orbital launch mount (rebuild) pad1-olm

    Now at Sanchez lot.

    Candidate at Starbase Pad 1 c-8266d2703d91 UNCONFIRMED

    2026-10-18 UNCONFIRMED note at P1 about pad1-olm c-8266d2703d91

    The crane Littler Larry was lifting the second new orbital launch mount leg into position at Pad 1, in breezy conditions.

    @VickiCocks15 X post Counts with a second source

  3. Pad 1 SQD arm (rebuild) pad1-sqd

    Now at Sanchez lot.

    2026-10-11 CONFIRMED note at SAN about pad1-sqd c-9c5f54525ea2

    Pad 1 SQD arm under construction in the Sanchez lot; TrackingTheSB says work on it continued steadily through the week of 5 Oct.

    @TrackingTheSB X post Confirms alone @RGVaerialphotos X post Counts with a second source

Activity

34 claims, newest first. An effect that names this pad, or a claim about hardware tied to it. Unconfirmed claims stay stamped.

  1. 2026-11-10 CONFIRMED note at P1 c-e5a6ffc5303f

    The second of four sloped wall sections was installed in the Pad 1 flame trench, and VickiCocks15 later saw another sloped trench wall section lifted into place.

    @NASASpaceflight X post Counts with a second source @VickiCocks15 X post Counts with a second source

  2. 2026-11-02 UNCONFIRMED note at P1 c-109fd456e3bc

    The dead-line spool for the Pad 1 drawworks reached the launch site, driving through the D1 gate toward the pad.

    @VickiCocks15 X post Counts with a second source

  3. 2026-10-30 UNCONFIRMED note at P1 c-2a1a1ddab0fe

    NSF reports the top deck deluge plates were lifted onto the Pad 1 launch mount during the week of Flight 15 static fires.

    NASASpaceflight Web page Counts with a second source @NASASpaceflight X post Counts with a second source

  4. 2026-10-27 UNCONFIRMED note at P1 c-326d880b23fb

    Work on the Pad 1 flame trench continues.

    @RGVaerialphotos X post Counts with a second source

  5. 2026-10-25 UNCONFIRMED note at P1 c-c74779406712

    TrackingTheSB weekly: this week the four legs that hold the orbital launch mount were installed at Pad 1 over a couple of days.

    @TrackingTheSB X post Confirms alone

  6. 2026-10-23 CONFIRMED note at P1 c-fe5eef2d2c97

    Another section of flame trench wall was lifted into place at Pad 1.

    @VickiCocks15 X post Counts with a second source @NASASpaceflight X post Counts with a second source

  7. 2026-10-22 UNCONFIRMED note at P1 c-e7e7b3cd27af

    The fourth launch mount leg was lifted into position at Pad 1.

    @VickiCocks15 X post Counts with a second source

  8. 2026-10-21 UNCONFIRMED note at P1 c-3d0e41a7c0af

    The Littler Larry crane lifted the third launch mount leg into place at Pad 1.

    @VickiCocks15 X post Counts with a second source

  9. 2026-10-18 UNCONFIRMED note at P1 about pad1-olm c-8266d2703d91

    The crane Littler Larry was lifting the second new orbital launch mount leg into position at Pad 1, in breezy conditions.

    @VickiCocks15 X post Counts with a second source

  10. 2026-10-18 CONFIRMED note at P1 about pad1-flame-deflector c-315c655dbad4

    TrackingTheSB weekly: this week teams lifted the centre flame bucket part into the Pad 1 trench and began installing the launch mount legs. The last flight from Pad 1 was Flight 11.

    @TrackingTheSB X post Confirms alone

  11. 2026-10-16 UNCONFIRMED note at P1 c-cd927e9de285

    A new piece of drawworks balcony wall was set in place at Pad 1.

    @VickiCocks15 X post Counts with a second source

  12. 2026-10-16 UNCONFIRMED note at P1 about pad1-flame-deflector c-b0b10ab55b94

    Teams at Pad 1 lifted a piece of the flame bucket into place as the pad rebuild takes shape.

    @RoughRidersShow X post Counts with a second source

  13. 2026-10-16 UNCONFIRMED note at P1 c-7baeefce1da2

    The flame trench apex support beam was lowered into the Pad 1 trench.

    @VickiCocks15 X post Counts with a second source

  14. 2026-10-15 UNCONFIRMED identify hardware Pad 1 orbital launch mount (rebuild) c-0cf5053e6dbd

    Identify the new Pad 1 orbital launch mount as hardware; its first leg went into the flame trench.

    @Blobifie X post Counts with a second source

  15. 2026-10-15 UNCONFIRMED note at P1 about pad1-olm c-c61dd0c20c22

    The first of the new Pad 1 orbital launch mount legs was installed into the flame trench.

    @Blobifie X post Counts with a second source @VickiCocks15 X post Counts with a second source

  16. 2026-10-15 UNCONFIRMED note at P1 c-2aa04b79217c

    Pad 1 tower base received walling work while the first Launch Mount leg was being lifted into position.

    @VickiCocks15 X post Counts with a second source

  17. 2026-10-11 CONFIRMED note at SAN about pad1-sqd c-9c5f54525ea2

    Pad 1 SQD arm under construction in the Sanchez lot; TrackingTheSB says work on it continued steadily through the week of 5 Oct.

    @TrackingTheSB X post Confirms alone @RGVaerialphotos X post Counts with a second source

  18. 2026-10-11 CONFIRMED note at SAN about pad1-olm c-30be9ab0ed78

    New Pad 1 orbital launch mount under construction in the Sanchez lot; TrackingTheSB says work on it continued steadily through the week of 5 Oct.

    @TrackingTheSB X post Confirms alone @RGVaerialphotos X post Counts with a second source

  19. 2026-10-11 CONFIRMED note at SAN about pad1-flame-deflector c-20437032bb02

    Pad 1 flame deflector under construction in the Sanchez lot; TrackingTheSB says work on it continued steadily through the week of 5 Oct.

    @TrackingTheSB X post Confirms alone @RGVaerialphotos X post Counts with a second source

  20. 2026-10-11 CONFIRMED identify hardware Pad 1 SQD arm (rebuild) c-924363991321

    Identify the new Pad 1 ship quick disconnect (SQD) arm as hardware, under construction in the Sanchez lot.

    @TrackingTheSB X post Confirms alone @RGVaerialphotos X post Counts with a second source

  21. 2026-10-11 CONFIRMED identify hardware Pad 1 flame deflector (rebuild) c-638757070511

    Identify the new Pad 1 flame deflector as hardware, under construction in the Sanchez lot alongside the new Pad 1 OLM and SQD arm.

    @TrackingTheSB X post Confirms alone @RGVaerialphotos X post Counts with a second source

  22. 2026-09-13 CONFIRMED note at P1 c-8adbfedefc93

    Reported 13 Sep 2026: Pad 1 tower had its roof reinstalled early in the week of 7 Sep, after it was taken down for modifications.

    @TrackingTheSB X post Confirms alone

  23. 2026-09-06 CONFIRMED note at P1 c-0e735138eefc

    Reported 6 Sep 2026: the weather tower on Tower 1 was removed that week so the protective roof could be lifted onto the tower.

    @TrackingTheSB X post Confirms alone

  24. 2025-10-13 CONFIRMED Flight 11 F11 NET 2025-10-13 at P1 c-a5ca421f05fc

    Flight 11 lifted off from Starbase Pad 1 on 13 Oct 2025 at 6:23 p.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  25. 2025-08-26 CONFIRMED Flight 10 F10 NET 2025-08-26 at P1 c-e98875e23500

    Flight 10 lifted off from Starbase Pad 1 on 26 Aug 2025 at 6:30 p.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  26. 2025-05-27 CONFIRMED Flight 9 F9 NET 2025-05-27 at P1 c-19314e83ec26

    Flight 9 lifted off from Starbase Pad 1 on 27 May 2025 at 6:36 p.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  27. 2025-03-06 CONFIRMED Flight 8 F8 NET 2025-03-06 at P1 c-b377cfd90471

    Flight 8 lifted off from Starbase Pad 1 on 6 Mar 2025 at 5:30 p.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  28. 2025-01-16 CONFIRMED Flight 7 F7 NET 2025-01-16 at P1 c-c65fa659f9ae

    Flight 7 lifted off from Starbase Pad 1 on 16 Jan 2025 at 4:37 p.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  29. 2024-11-19 CONFIRMED Flight 6 F6 NET 2024-11-19 at P1 c-4b4c882617ff

    Flight 6 lifted off from Starbase Pad 1 on 19 Nov 2024.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  30. 2024-10-13 CONFIRMED Flight 5 F5 NET 2024-10-13 at P1 c-30ce77b2360d

    Flight 5 lifted off from Starbase Pad 1 on 13 Oct 2024.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  31. 2024-06-06 CONFIRMED Flight 4 F4 NET 2024-06-06 at P1 c-c1d4f6e77437

    Flight 4 lifted off from Starbase Pad 1 on 6 Jun 2024 at 7:50 a.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  32. 2024-03-14 CONFIRMED Flight 3 F3 NET 2024-03-14 at P1 c-46e23605cf75

    Flight 3 lifted off from Starbase Pad 1 on 14 Mar 2024 at 8:25 a.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  33. 2023-11-18 CONFIRMED Flight 2 F2 NET 2023-11-18 at P1 c-78db71b30a1e

    Flight 2 lifted off from Starbase Pad 1 on 18 Nov 2023 at 7:02 a.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  34. 2023-04-20 CONFIRMED Flight 1 F1 NET 2023-04-20 at P1 c-79dfbb3a9457

    Flight 1 lifted off from the orbital launch pad at Starbase, which the SpaceX launches list names Pad 1, on 20 Apr 2023 at 8:33 a.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

Flights

11 schedules that name this pad. A NET is not a liftoff.

  1. Flight 1 NET 2023-04-20 2023-04-20 CONFIRMED Flight 1 F1 NET 2023-04-20 at P1 c-79dfbb3a9457

    Flight 1 lifted off from the orbital launch pad at Starbase, which the SpaceX launches list names Pad 1, on 20 Apr 2023 at 8:33 a.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  2. Flight 2 NET 2023-11-18 2023-11-18 CONFIRMED Flight 2 F2 NET 2023-11-18 at P1 c-78db71b30a1e

    Flight 2 lifted off from Starbase Pad 1 on 18 Nov 2023 at 7:02 a.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  3. Flight 3 NET 2024-03-14 2024-03-14 CONFIRMED Flight 3 F3 NET 2024-03-14 at P1 c-46e23605cf75

    Flight 3 lifted off from Starbase Pad 1 on 14 Mar 2024 at 8:25 a.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  4. Flight 4 NET 2024-06-06 2024-06-06 CONFIRMED Flight 4 F4 NET 2024-06-06 at P1 c-c1d4f6e77437

    Flight 4 lifted off from Starbase Pad 1 on 6 Jun 2024 at 7:50 a.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  5. Flight 5 NET 2024-10-13 2024-10-13 CONFIRMED Flight 5 F5 NET 2024-10-13 at P1 c-30ce77b2360d

    Flight 5 lifted off from Starbase Pad 1 on 13 Oct 2024.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  6. Flight 6 NET 2024-11-19 2024-11-19 CONFIRMED Flight 6 F6 NET 2024-11-19 at P1 c-4b4c882617ff

    Flight 6 lifted off from Starbase Pad 1 on 19 Nov 2024.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  7. Flight 7 NET 2025-01-16 2025-01-16 CONFIRMED Flight 7 F7 NET 2025-01-16 at P1 c-c65fa659f9ae

    Flight 7 lifted off from Starbase Pad 1 on 16 Jan 2025 at 4:37 p.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  8. Flight 8 NET 2025-03-06 2025-03-06 CONFIRMED Flight 8 F8 NET 2025-03-06 at P1 c-b377cfd90471

    Flight 8 lifted off from Starbase Pad 1 on 6 Mar 2025 at 5:30 p.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  9. Flight 9 NET 2025-05-27 2025-05-27 CONFIRMED Flight 9 F9 NET 2025-05-27 at P1 c-19314e83ec26

    Flight 9 lifted off from Starbase Pad 1 on 27 May 2025 at 6:36 p.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  10. Flight 10 NET 2025-08-26 2025-08-26 CONFIRMED Flight 10 F10 NET 2025-08-26 at P1 c-e98875e23500

    Flight 10 lifted off from Starbase Pad 1 on 26 Aug 2025 at 6:30 p.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  11. Flight 11 NET 2025-10-13 2025-10-13 CONFIRMED Flight 11 F11 NET 2025-10-13 at P1 c-a5ca421f05fc

    Flight 11 lifted off from Starbase Pad 1 on 13 Oct 2025 at 6:23 p.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

Starbase

Starbase Pad 2 P2

Launch pad

Ground systems

One mark per claim whose effect at is this pad, or whose about names hardware the ledger places here. The earliest word in the summary picks the lane. Words that start together keep the longer one. A summary with none of them is Other. Filled marks are confirmed. Hollow marks are unconfirmed, and the table keeps the UNCONFIRMED stamp.

Starbase Pad 2 ground systems, 8 Sept to 15 NovLaunch mount / legsChopsticks / towerDeluge / water tanksBQD / SQDFlame deflectorTank farm / propellantOther8 Sept15 Sept22 Sept29 Sept6 Oct13 Oct20 Oct27 Oct3 Nov10 Nov15 Nov2026-09-08 Launch mount / legs: Pad 2 OLM ran a full launch-to-catch deluge operation.2026-09-10 Launch mount / legs: Pad 2 OLM ran a further deluge test.2026-09-10 Chopsticks / tower: Ship catch rehearsal at Pad 2: S42 was placed deep in the chopsticks and lifted a few meters, then the chopstick pushers moved it to the stabilizer engagement position and the stabilizers were engaged.2026-09-10 Chopsticks / tower: Pad 2 chopsticks held S42 deep in the arms and lifted it a few meters during catch rehearsal.2026-09-12 BQD / SQD: Ship catch rehearsal at Pad 2: S42 was lifted to catch height and back down to SQD height, the SQD rotated in and connected, then S42 was rotated, flaps tucked, and lowered onto its transport stand.2026-09-12 BQD / SQD: Pad 2 SQD arm rotated in and connected to S42 at SQD height during catch rehearsal, a rehearsal of post-catch ship safing.2026-10-14 Chopsticks / tower UNCONFIRMED: After damper work on 14 Oct (local), the Pad 2 chopsticks were raised and lowered a few times with checks in one pause; no arm swings were seen. The Deadline balcony at the base of Tower 2 received extra cladding the same day.2026-10-15 Chopsticks / tower UNCONFIRMED: Blobifie: SpaceX ran catch testing with the Pad 2 chopsticks at the top of the tower, and workers were seen celebrating at the top of the tower later in the day. NSF's Starbase summary of 15 Oct also shows the chopsticks run to the top of Tower 2 for high-speed tests.2026-10-16 Chopsticks / tower UNCONFIRMED: Further chopstick testing at Pad 2.2026-10-18 Deluge / water tanks UNCONFIRMED: TrackingTheSB weekly: late on 18 Oct the dancefloor service structure was removed from Pad 2 after post Flight 14 checkouts, then four full deluge tests including the top plate ran over 48 hours and the booster quick disconnects did a purge.2026-10-19 Launch mount / legs UNCONFIRMED: The launch mount service structure has been removed from Pad 2 and rolled back for storage near the D1 gate at the launch complex.2026-10-20 Chopsticks / tower: Chopstick testing at the top of the Pad 2 tower, with the deluge system activated during it; Blobifie reports both a launch and a landing deluge test.2026-10-21 Deluge / water tanks: Pad 2 ran two water deluge tests about seven to eight minutes apart, one simulating a launch and one a catch, for the second day running. VickiCocks15 says the pressure looked higher than the day before.2026-10-21 BQD / SQD UNCONFIRMED: Booster quick disconnects (BQDs) at Starbase Pad 2 purging, which the post hopes is ahead of Booster 22 arriving soon.2026-10-22 Deluge / water tanks UNCONFIRMED: In the same Pad 2 test thread, the hold down clamps were tested with a few individual retract and extend moves and a simultaneous retract, then one visible clamp extended and retracted alone; the deluge was then tested without the top deck.2026-10-22 BQD / SQD UNCONFIRMED: The booster quick disconnects (BQDs) at Pad 2 were tested with a few slow extend and retract moves, ending in a fast retract.2026-10-22 Deluge / water tanks UNCONFIRMED: Pad 2 completed another launch and landing deluge test.2026-10-23 Other: The SpaceX LR11000 crane at the Starbase launch site was lowered, which TrackingTheSB links to upcoming testing.2026-10-24 Other UNCONFIRMED: Littler Larry, the second SpaceX owned LR11000 crane at the launch site, was laid down during the Booster 22 lift on the morning of 24 Oct, following Maarvin, which was laid down on 23 Oct.2026-10-24 BQD / SQD UNCONFIRMED: With cranes down, Booster 22 on the mount, BQDs engaged and blast doors closed, VickiCocks15 says Pad 2 looks locked up ahead of testing planned for 25 Oct.2026-10-24 Launch mount / legs: Booster 22 was lifted onto the Pad 2 orbital launch mount and lowered onto it on the afternoon of 24 Oct.2026-10-25 Other: The booster transport stand left the Pad 2 launch site ahead of the Booster 22 static fire; VickiCocks15 says it was moved to gate D1 for safety.2026-10-25 Chopsticks / tower UNCONFIRMED: Ahead of the Booster 22 static fire, the Pad 2 chopsticks were opened and raised to launch position and the DSS was tested, as stated by VickiCocks15.2026-10-25 Other: Booster 22 completed a static fire test on Pad 2 at Starbase. Blobifie reports the burn lasted more than 15 seconds.2026-10-25 Other UNCONFIRMED: Booster 22 was detanked after its static fire on Pad 2.2026-10-25 Other UNCONFIRMED: Highway 4 and Boca Chica Beach were closed on 25 Oct from 7 AM to 7 PM ET for SpaceX spaceflight activities, with Monday 26 Oct as the backup, per FelixSchlang; Blobifie reported the road closed ahead of the static fire.2026-10-25 Other: SpaceX called the Booster 22 static fire for Flight 15 a full duration 33-engine static fire.2026-10-25 Chopsticks / tower UNCONFIRMED: After the static fire, the Pad 2 chopsticks descended and closed in around Booster 22, as stated by VickiCocks15.2026-10-25 Launch mount / legs: Booster 22 was lifted off the Pad 2 launch mount to catch height at the top of the tower, then set on the booster transport ring for its trip back to Mega Bay 1 for final flight preparations.2026-10-26 BQD / SQD UNCONFIRMED: Blobifie says Ship 43 went back onto its transport stand after the Pad 2 SQD connection test, and that the post-flight safing practice went much smoother than the same test with Ship 42.2026-10-26 Other UNCONFIRMED: The City of Starbase Production to Pad road delay on Mon 26 Oct was extended from 10:00 to 14:00 CT to 10:00 to 15:00 CT, and the backup Highway 4 and beach closure for that day was revoked.2026-10-26 Chopsticks / tower: At Pad 2 the chopsticks lifted Ship 43 above its transport stand and up to the top of the tower, then lowered it to the height of the ship quick disconnect (SQD) arm, which connected to it: practice for post-catch safing operations.2026-10-27 Chopsticks / tower UNCONFIRMED: Blobifie says Ship 43 was moved to the middle of the Pad 2 chopsticks and lifted, a test simulating moving the ship forward after a catch so the stabilizer arms can engage.2026-10-27 Chopsticks / tower: Ship 43 was lifted by the Pad 2 chopsticks with the landing rails deployed and moved back and forth, checking the rails and push rods after the previous night's SQD interface tests; Blobifie says this post-catch pusher test went much smoother than with Ship 42.2026-11-01 Launch mount / legs UNCONFIRMED: VickiCocks15 says Launch Mount 2 is getting a spruce-up, which she links to the Flight 15 live stream.2026-11-01 Other UNCONFIRMED: Pad 2 has been painted a green colour.2026-11-03 BQD / SQD UNCONFIRMED: VickiCocks15 says work was going on at both the LOX and the CH4 booster quick disconnects (BQDs) at Pad 2, to make sure they are ready for Flight 15.2026-11-03 Other UNCONFIRMED: FelixSchlang says SpaceX recently lifted Ship 43 to catch height at Pad 2 for catch practice (photo by Jordan Guidry, WAI Media).2026-11-05 Deluge / water tanks UNCONFIRMED: Pad 2 deluge system testing continued on 5 Nov: VickiCocks15 recorded a launch-and-catch deluge scenario earlier and one further Pad-2 deluge test that night; Blobifie reports about three deluge tests plus catch testing over roughly 48 hours; RGVaerialphotos posted a Pad 2 chopstick and deluge testing timelapse.2026-11-06 Launch mount / legs UNCONFIRMED: Pad 2 on 6 Nov: VickiCocks15 reports booster hold-down clamp testing and the launch mount service structure moved closer to Pad 1 in the morning. That evening the chopsticks were raised part way up the tower, the BQDs were extended, purged and retracted, deluge tests ran the launch and catch sequences again, then the BQDs were extended again and the chopsticks lowered. RGVaerialphotos posted the deluge testing.2026-11-08 Chopsticks / tower: Pad 2 on the morning of 8 Nov: the chopsticks rose up the tower, the launch mount top deck and the deluge farm were primed, and launch and catch deluge run-throughs were performed. The TrackingTheSB weekly counts seven Pad 2 deluge tests in the week to 8 Nov.2026-11-08 BQD / SQD UNCONFIRMED: VickiCocks15 says the Pad 2 BQD was extended and retracted, and the booster hold-down clamps were retracted and extended one by one and then retracted together, on the evening of 8 Nov.2026-11-10 Chopsticks / tower: Booster 22 was lifted to the top of the Pad 2 tower, moved around on the chopsticks using the pusher system, and lowered onto the orbital launch mount. VickiCocks15 later described it as settled on the mount with the clamps lined up.2026-11-11 Chopsticks / tower: The Pad 2 chopsticks released Booster 22 and descended the tower and the SQD arm was reset. Workers then spent several hours around B22's catch pins and grid fins, the booster transport stand returned to the build site, the SQD was retracted and the chopsticks went back to the booster support position.2026-11-11 Chopsticks / tower UNCONFIRMED: VickiCocks15 says the Pad 2 chopsticks released Booster 22 again on 11 Nov and returned to the side of the launch mount, with the crew lift that had worked on the grid fins moved away, then later the chopsticks moved back up the tower and hugged Booster 22 once more. She also says one of the chopstick sims was put back in the Super Crusher cage, suggesting testing of 43.1 is not finished.2026-11-12 Other: Ship 42 was driven to the Starbase launch site on 12 Nov, lifted onto Booster 22 at Pad 2 and stacked for Flight 15. SpaceX posted that Ship 42 moves to the Starbase pad ahead of launch, and NASASpaceflight posted the Ship 42 lift.2026-11-13 BQD / SQD UNCONFIRMED: VickiCocks15 says the SQD access platform was retracted, the SQD attached to Ship 42, and a fast retract and reattach test performed. TrackingTheSB also says the SQD was being connected to Ship 42.2026-11-14 BQD / SQD UNCONFIRMED: LabPadre says the stabilizer pins engaged on Ship 42 as it lowered to connect the SQD, and later that the SQD attached to S42 and residual detanking began; Blobifie also says the SQD arm attached to allow detanking and safing.2026-11-14 Chopsticks / tower UNCONFIRMED: TrackingTheSB says the Pad 2 chopsticks, which had sat at the bottom of the tower after the Booster 22 divert, returned to catch height; LabPadre also reports the chopsticks raised back to the catch position after a brief inspection by workers.2026-11-15 BQD / SQD UNCONFIRMED: VickiCocks15 says the LM-2 hold-down clamps and both BQDs have been extended after Flight 15.
DateLaneSummaryClaim
2026-09-08Launch mount / legsPad 2 OLM ran a full launch-to-catch deluge operation.c-42cd710b9851
2026-09-10Launch mount / legsPad 2 OLM ran a further deluge test.c-509afe456ce6
2026-09-10Chopsticks / towerShip catch rehearsal at Pad 2: S42 was placed deep in the chopsticks and lifted a few meters, then the chopstick pushers moved it to the stabilizer engagement position and the stabilizers were engaged.c-5e1953d56a83
2026-09-10Chopsticks / towerPad 2 chopsticks held S42 deep in the arms and lifted it a few meters during catch rehearsal.c-bb7b05249641
2026-09-12BQD / SQDShip catch rehearsal at Pad 2: S42 was lifted to catch height and back down to SQD height, the SQD rotated in and connected, then S42 was rotated, flaps tucked, and lowered onto its transport stand.c-3c911339ea58
2026-09-12BQD / SQDPad 2 SQD arm rotated in and connected to S42 at SQD height during catch rehearsal, a rehearsal of post-catch ship safing.c-19665b5bfbaf
2026-10-14Chopsticks / towerAfter damper work on 14 Oct (local), the Pad 2 chopsticks were raised and lowered a few times with checks in one pause; no arm swings were seen. The Deadline balcony at the base of Tower 2 received extra cladding the same day.c-917e300f41bf UNCONFIRMED
2026-10-15Chopsticks / towerBlobifie: SpaceX ran catch testing with the Pad 2 chopsticks at the top of the tower, and workers were seen celebrating at the top of the tower later in the day. NSF's Starbase summary of 15 Oct also shows the chopsticks run to the top of Tower 2 for high-speed tests.c-289f4e9f12d0 UNCONFIRMED
2026-10-16Chopsticks / towerFurther chopstick testing at Pad 2.c-793f722ba51a UNCONFIRMED
2026-10-18Deluge / water tanksTrackingTheSB weekly: late on 18 Oct the dancefloor service structure was removed from Pad 2 after post Flight 14 checkouts, then four full deluge tests including the top plate ran over 48 hours and the booster quick disconnects did a purge.c-351703f455c4 UNCONFIRMED
2026-10-19Launch mount / legsThe launch mount service structure has been removed from Pad 2 and rolled back for storage near the D1 gate at the launch complex.c-2354811f6b72 UNCONFIRMED
2026-10-20Chopsticks / towerChopstick testing at the top of the Pad 2 tower, with the deluge system activated during it; Blobifie reports both a launch and a landing deluge test.c-4548053919dc
2026-10-21Deluge / water tanksPad 2 ran two water deluge tests about seven to eight minutes apart, one simulating a launch and one a catch, for the second day running. VickiCocks15 says the pressure looked higher than the day before.c-96b09ca5a132
2026-10-21BQD / SQDBooster quick disconnects (BQDs) at Starbase Pad 2 purging, which the post hopes is ahead of Booster 22 arriving soon.c-ba450eb5e0c5 UNCONFIRMED
2026-10-22Deluge / water tanksIn the same Pad 2 test thread, the hold down clamps were tested with a few individual retract and extend moves and a simultaneous retract, then one visible clamp extended and retracted alone; the deluge was then tested without the top deck.c-26bf5a57aaaf UNCONFIRMED
2026-10-22BQD / SQDThe booster quick disconnects (BQDs) at Pad 2 were tested with a few slow extend and retract moves, ending in a fast retract.c-2703ef43949c UNCONFIRMED
2026-10-22Deluge / water tanksPad 2 completed another launch and landing deluge test.c-7c41daa05375 UNCONFIRMED
2026-10-23OtherThe SpaceX LR11000 crane at the Starbase launch site was lowered, which TrackingTheSB links to upcoming testing.c-87c7c1e990a3
2026-10-24OtherLittler Larry, the second SpaceX owned LR11000 crane at the launch site, was laid down during the Booster 22 lift on the morning of 24 Oct, following Maarvin, which was laid down on 23 Oct.c-58c6f7d92d91 UNCONFIRMED
2026-10-24BQD / SQDWith cranes down, Booster 22 on the mount, BQDs engaged and blast doors closed, VickiCocks15 says Pad 2 looks locked up ahead of testing planned for 25 Oct.c-eab5f4451ac8 UNCONFIRMED
2026-10-24Launch mount / legsBooster 22 was lifted onto the Pad 2 orbital launch mount and lowered onto it on the afternoon of 24 Oct.c-27f38f636d95
2026-10-25OtherThe booster transport stand left the Pad 2 launch site ahead of the Booster 22 static fire; VickiCocks15 says it was moved to gate D1 for safety.c-2ed4b5250957
2026-10-25Chopsticks / towerAhead of the Booster 22 static fire, the Pad 2 chopsticks were opened and raised to launch position and the DSS was tested, as stated by VickiCocks15.c-6b8e42a0065e UNCONFIRMED
2026-10-25OtherBooster 22 completed a static fire test on Pad 2 at Starbase. Blobifie reports the burn lasted more than 15 seconds.c-7497db7affd7
2026-10-25OtherBooster 22 was detanked after its static fire on Pad 2.c-e368e18c7435 UNCONFIRMED
2026-10-25OtherHighway 4 and Boca Chica Beach were closed on 25 Oct from 7 AM to 7 PM ET for SpaceX spaceflight activities, with Monday 26 Oct as the backup, per FelixSchlang; Blobifie reported the road closed ahead of the static fire.c-8090fbd8f383 UNCONFIRMED
2026-10-25OtherSpaceX called the Booster 22 static fire for Flight 15 a full duration 33-engine static fire.c-f3863dfdbddf
2026-10-25Chopsticks / towerAfter the static fire, the Pad 2 chopsticks descended and closed in around Booster 22, as stated by VickiCocks15.c-e02fc7cffe65 UNCONFIRMED
2026-10-25Launch mount / legsBooster 22 was lifted off the Pad 2 launch mount to catch height at the top of the tower, then set on the booster transport ring for its trip back to Mega Bay 1 for final flight preparations.c-74a0e6a4213e
2026-10-26BQD / SQDBlobifie says Ship 43 went back onto its transport stand after the Pad 2 SQD connection test, and that the post-flight safing practice went much smoother than the same test with Ship 42.c-a78aa194f37e UNCONFIRMED
2026-10-26OtherThe City of Starbase Production to Pad road delay on Mon 26 Oct was extended from 10:00 to 14:00 CT to 10:00 to 15:00 CT, and the backup Highway 4 and beach closure for that day was revoked.c-f735a270f13d UNCONFIRMED
2026-10-26Chopsticks / towerAt Pad 2 the chopsticks lifted Ship 43 above its transport stand and up to the top of the tower, then lowered it to the height of the ship quick disconnect (SQD) arm, which connected to it: practice for post-catch safing operations.c-eec7f163ae4b
2026-10-27Chopsticks / towerBlobifie says Ship 43 was moved to the middle of the Pad 2 chopsticks and lifted, a test simulating moving the ship forward after a catch so the stabilizer arms can engage.c-c65eaa010472 UNCONFIRMED
2026-10-27Chopsticks / towerShip 43 was lifted by the Pad 2 chopsticks with the landing rails deployed and moved back and forth, checking the rails and push rods after the previous night's SQD interface tests; Blobifie says this post-catch pusher test went much smoother than with Ship 42.c-3a07c5d16bc0
2026-11-01Launch mount / legsVickiCocks15 says Launch Mount 2 is getting a spruce-up, which she links to the Flight 15 live stream.c-1988c2e30d4d UNCONFIRMED
2026-11-01OtherPad 2 has been painted a green colour.c-810054334135 UNCONFIRMED
2026-11-03BQD / SQDVickiCocks15 says work was going on at both the LOX and the CH4 booster quick disconnects (BQDs) at Pad 2, to make sure they are ready for Flight 15.c-148518874adb UNCONFIRMED
2026-11-03OtherFelixSchlang says SpaceX recently lifted Ship 43 to catch height at Pad 2 for catch practice (photo by Jordan Guidry, WAI Media).c-a459d50add72 UNCONFIRMED
2026-11-05Deluge / water tanksPad 2 deluge system testing continued on 5 Nov: VickiCocks15 recorded a launch-and-catch deluge scenario earlier and one further Pad-2 deluge test that night; Blobifie reports about three deluge tests plus catch testing over roughly 48 hours; RGVaerialphotos posted a Pad 2 chopstick and deluge testing timelapse.c-6943ede4665c UNCONFIRMED
2026-11-06Launch mount / legsPad 2 on 6 Nov: VickiCocks15 reports booster hold-down clamp testing and the launch mount service structure moved closer to Pad 1 in the morning. That evening the chopsticks were raised part way up the tower, the BQDs were extended, purged and retracted, deluge tests ran the launch and catch sequences again, then the BQDs were extended again and the chopsticks lowered. RGVaerialphotos posted the deluge testing.c-aa78316a0195 UNCONFIRMED
2026-11-08Chopsticks / towerPad 2 on the morning of 8 Nov: the chopsticks rose up the tower, the launch mount top deck and the deluge farm were primed, and launch and catch deluge run-throughs were performed. The TrackingTheSB weekly counts seven Pad 2 deluge tests in the week to 8 Nov.c-54096c854a91
2026-11-08BQD / SQDVickiCocks15 says the Pad 2 BQD was extended and retracted, and the booster hold-down clamps were retracted and extended one by one and then retracted together, on the evening of 8 Nov.c-838ff6ce684e UNCONFIRMED
2026-11-10Chopsticks / towerBooster 22 was lifted to the top of the Pad 2 tower, moved around on the chopsticks using the pusher system, and lowered onto the orbital launch mount. VickiCocks15 later described it as settled on the mount with the clamps lined up.c-b531e3eed92a
2026-11-11Chopsticks / towerThe Pad 2 chopsticks released Booster 22 and descended the tower and the SQD arm was reset. Workers then spent several hours around B22's catch pins and grid fins, the booster transport stand returned to the build site, the SQD was retracted and the chopsticks went back to the booster support position.c-0858d3b8b1aa
2026-11-11Chopsticks / towerVickiCocks15 says the Pad 2 chopsticks released Booster 22 again on 11 Nov and returned to the side of the launch mount, with the crew lift that had worked on the grid fins moved away, then later the chopsticks moved back up the tower and hugged Booster 22 once more. She also says one of the chopstick sims was put back in the Super Crusher cage, suggesting testing of 43.1 is not finished.c-ae0cf69044a0 UNCONFIRMED
2026-11-12OtherShip 42 was driven to the Starbase launch site on 12 Nov, lifted onto Booster 22 at Pad 2 and stacked for Flight 15. SpaceX posted that Ship 42 moves to the Starbase pad ahead of launch, and NASASpaceflight posted the Ship 42 lift.c-a66e8f14aa7d
2026-11-13BQD / SQDVickiCocks15 says the SQD access platform was retracted, the SQD attached to Ship 42, and a fast retract and reattach test performed. TrackingTheSB also says the SQD was being connected to Ship 42.c-e45478ef161b UNCONFIRMED
2026-11-14BQD / SQDLabPadre says the stabilizer pins engaged on Ship 42 as it lowered to connect the SQD, and later that the SQD attached to S42 and residual detanking began; Blobifie also says the SQD arm attached to allow detanking and safing.c-ed6998be1b80 UNCONFIRMED
2026-11-14Chopsticks / towerTrackingTheSB says the Pad 2 chopsticks, which had sat at the bottom of the tower after the Booster 22 divert, returned to catch height; LabPadre also reports the chopsticks raised back to the catch position after a brief inspection by workers.c-f37e02c4537a UNCONFIRMED
2026-11-15BQD / SQDVickiCocks15 says the LM-2 hold-down clamps and both BQDs have been extended after Flight 15.c-b030414997e1 UNCONFIRMED
Launch mount / legs
orbital launch mount, launch mount, mount legs, mount leg, olm
Chopsticks / tower
chopsticks, chopstick, towers, tower
Deluge / water tanks
deluge, water tanks, water tank
BQD / SQD
quick disconnects, quick disconnect, quick-disconnects, quick-disconnect, bqds, bqd, sqds, sqd
Flame deflector
flame deflector, deflector, flame trench, flame bucket
Tank farm / propellant
tank farm, propellant
Other
no word from the lanes above

Components

2 pieces from the hardware register. Now at is the last confirmed place a source stated, or an unconfirmed place stamped as such when nothing confirms one. A newer unconfirmed place sits beside it as a candidate.

  1. Pad 2 chopsticks pad2-chopsticks

    Now at Starbase Pad 2.

    2026-10-16 UNCONFIRMED note at P2 about pad2-chopsticks c-793f722ba51a

    Further chopstick testing at Pad 2.

    @VickiCocks15 X post Counts with a second source

  2. Pad 2 SQD arm pad2-sqd

    Now at Starbase Pad 2.

    2026-09-12 CONFIRMED note at P2 about pad2-sqd c-19665b5bfbaf

    Pad 2 SQD arm rotated in and connected to S42 at SQD height during catch rehearsal, a rehearsal of post-catch ship safing.

    @TrackingTheSB X post Confirms alone

Activity

64 claims, newest first. An effect that names this pad, or a claim about hardware tied to it. Unconfirmed claims stay stamped.

  1. 2026-11-15 UNCONFIRMED note at P2 c-b030414997e1

    VickiCocks15 says the LM-2 hold-down clamps and both BQDs have been extended after Flight 15.

    @VickiCocks15 X post Counts with a second source

  2. 2026-11-14 UNCONFIRMED note at P2 c-f37e02c4537a

    TrackingTheSB says the Pad 2 chopsticks, which had sat at the bottom of the tower after the Booster 22 divert, returned to catch height; LabPadre also reports the chopsticks raised back to the catch position after a brief inspection by workers.

    @TrackingTheSB X post Confirms alone @LabPadre X post Counts with a second source

  3. 2026-11-14 UNCONFIRMED note at P2 about S42 c-ed6998be1b80

    LabPadre says the stabilizer pins engaged on Ship 42 as it lowered to connect the SQD, and later that the SQD attached to S42 and residual detanking began; Blobifie also says the SQD arm attached to allow detanking and safing.

    @LabPadre X post Counts with a second source @Blobifie X post Counts with a second source

  4. 2026-11-13 UNCONFIRMED note at P2 about S42 c-e45478ef161b

    VickiCocks15 says the SQD access platform was retracted, the SQD attached to Ship 42, and a fast retract and reattach test performed. TrackingTheSB also says the SQD was being connected to Ship 42.

    @VickiCocks15 X post Counts with a second source @TrackingTheSB X post Confirms alone

  5. 2026-11-12 CONFIRMED note at P2 about S42 c-a66e8f14aa7d

    Ship 42 was driven to the Starbase launch site on 12 Nov, lifted onto Booster 22 at Pad 2 and stacked for Flight 15. SpaceX posted that Ship 42 moves to the Starbase pad ahead of launch, and NASASpaceflight posted the Ship 42 lift.

    @SpaceX X post Confirms alone @NASASpaceflight X post Counts with a second source @VickiCocks15 X post Counts with a second source

  6. 2026-11-11 UNCONFIRMED note at P2 about B22 c-ae0cf69044a0

    VickiCocks15 says the Pad 2 chopsticks released Booster 22 again on 11 Nov and returned to the side of the launch mount, with the crew lift that had worked on the grid fins moved away, then later the chopsticks moved back up the tower and hugged Booster 22 once more. She also says one of the chopstick sims was put back in the Super Crusher cage, suggesting testing of 43.1 is not finished.

    @VickiCocks15 X post Counts with a second source @VickiCocks15 X post Counts with a second source @VickiCocks15 X post Counts with a second source

  7. 2026-11-11 CONFIRMED note at P2 about B22 c-0858d3b8b1aa

    The Pad 2 chopsticks released Booster 22 and descended the tower and the SQD arm was reset. Workers then spent several hours around B22's catch pins and grid fins, the booster transport stand returned to the build site, the SQD was retracted and the chopsticks went back to the booster support position.

    @VickiCocks15 X post Counts with a second source @VickiCocks15 X post Counts with a second source @Blobifie X post Counts with a second source @Blobifie X post Counts with a second source

  8. 2026-11-10 CONFIRMED note at P2 about B22 c-b531e3eed92a

    Booster 22 was lifted to the top of the Pad 2 tower, moved around on the chopsticks using the pusher system, and lowered onto the orbital launch mount. VickiCocks15 later described it as settled on the mount with the clamps lined up.

    @RGVaerialphotos X post Counts with a second source @LabPadre X post Counts with a second source @TrackingTheSB X post Confirms alone @Blobifie X post Counts with a second source @VickiCocks15 X post Counts with a second source

  9. 2026-11-09 CONFIRMED transport B22 from MB1 to P2 c-a6c68d05514b

    Booster 22 left the production site and arrived at the Pad 2 launch site on the evening of 9 Nov (Texas time), for Flight 15. Trackers posted it as T-93 hours.

    @LabPadre X post Counts with a second source @TrackingTheSB X post Confirms alone @RGVaerialphotos X post Counts with a second source @StarshipGazer X post Counts with a second source

  10. 2026-11-08 UNCONFIRMED note at P2 c-838ff6ce684e

    VickiCocks15 says the Pad 2 BQD was extended and retracted, and the booster hold-down clamps were retracted and extended one by one and then retracted together, on the evening of 8 Nov.

    @VickiCocks15 X post Counts with a second source @VickiCocks15 X post Counts with a second source

  11. 2026-11-08 CONFIRMED note at P2 c-54096c854a91

    Pad 2 on the morning of 8 Nov: the chopsticks rose up the tower, the launch mount top deck and the deluge farm were primed, and launch and catch deluge run-throughs were performed. The TrackingTheSB weekly counts seven Pad 2 deluge tests in the week to 8 Nov.

    @VickiCocks15 X post Counts with a second source @LabPadre X post Counts with a second source @RGVaerialphotos X post Counts with a second source @TrackingTheSB X post Confirms alone

  12. 2026-11-07 CONFIRMED F15 NET 2026-11-13 at P2 c-638524a443e2

    SpaceX says Flight 15 is preparing to launch as soon as Friday 13 Nov 2026, pending regulatory approval, from Starbase. NSF says SpaceX tested the launch site systems ahead of rolling both vehicles to Pad 2.

    SpaceX Web page Confirms alone @SpaceX X post Confirms alone @NASASpaceflight X post Counts with a second source

  13. 2026-11-06 UNCONFIRMED note at P2 c-aa78316a0195

    Pad 2 on 6 Nov: VickiCocks15 reports booster hold-down clamp testing and the launch mount service structure moved closer to Pad 1 in the morning. That evening the chopsticks were raised part way up the tower, the BQDs were extended, purged and retracted, deluge tests ran the launch and catch sequences again, then the BQDs were extended again and the chopsticks lowered. RGVaerialphotos posted the deluge testing.

    @VickiCocks15 X post Counts with a second source @VickiCocks15 X post Counts with a second source @VickiCocks15 X post Counts with a second source @VickiCocks15 X post Counts with a second source @VickiCocks15 X post Counts with a second source @VickiCocks15 X post Counts with a second source @RGVaerialphotos X post Counts with a second source

  14. 2026-11-05 UNCONFIRMED note at P2 c-6943ede4665c

    Pad 2 deluge system testing continued on 5 Nov: VickiCocks15 recorded a launch-and-catch deluge scenario earlier and one further Pad-2 deluge test that night; Blobifie reports about three deluge tests plus catch testing over roughly 48 hours; RGVaerialphotos posted a Pad 2 chopstick and deluge testing timelapse.

    @VickiCocks15 X post Counts with a second source @VickiCocks15 X post Counts with a second source @Blobifie X post Counts with a second source @RGVaerialphotos X post Counts with a second source

  15. 2026-11-05 UNCONFIRMED Flight 15 F15 NET 2026-11-13 at P2 c-b2adfdd0de4b

    Flight 15 moved one day to NET 13 Nov 2026 per the Nov 5 CADENA FAA planning slide (was 12 Nov). LabPadre, FelixSchlang and lewisknaggs42 all cite the slide; LabPadre notes these are tentative planning dates, not NOTAMs. No Flight 15 launch licence is public yet.

    @LabPadre X post Counts with a second source @FelixSchlang X post Counts with a second source @lewisknaggs42 X post Counts with a second source

  16. 2026-11-03 UNCONFIRMED note at P2 about S43 c-a459d50add72

    FelixSchlang says SpaceX recently lifted Ship 43 to catch height at Pad 2 for catch practice (photo by Jordan Guidry, WAI Media).

    @FelixSchlang X post Counts with a second source

  17. 2026-11-03 UNCONFIRMED note at P2 c-148518874adb

    VickiCocks15 says work was going on at both the LOX and the CH4 booster quick disconnects (BQDs) at Pad 2, to make sure they are ready for Flight 15.

    @VickiCocks15 X post Counts with a second source

  18. 2026-11-01 UNCONFIRMED note at P2 c-810054334135

    Pad 2 has been painted a green colour.

    @Blobifie X post Counts with a second source

  19. 2026-11-01 UNCONFIRMED note at P2 c-1988c2e30d4d

    VickiCocks15 says Launch Mount 2 is getting a spruce-up, which she links to the Flight 15 live stream.

    @VickiCocks15 X post Counts with a second source

  20. 2026-10-29 UNCONFIRMED Flight 15 F15 NET 2026-11-12 at P2 c-f99b81d052de

    Flight 15 (Booster 22 and Ship 42) moved 4 days to NET 12 Nov 2026 per CADENA and a new FAA planning slide, which earlier listed 8 Nov. The FAA slide is a planning date, not a SpaceX date, and no Flight 15 launch licence is public yet.

    @LabPadre X post Counts with a second source @FelixSchlang X post Counts with a second source @lewisknaggs42 X post Counts with a second source @NASASpaceflight X post Counts with a second source @StarshipGazer X post Counts with a second source

  21. 2026-10-27 CONFIRMED transport S43 from P2 to MB2 c-ce15947922bf

    Ship 43 left Pad 2 late on 27 Oct (local time) after its chopstick tests, arrived back at the production site and entered Mega Bay 2.

    @TrackingTheSB X post Confirms alone @TrackingTheSB X post Confirms alone @Blobifie X post Counts with a second source @RGVaerialphotos X post Counts with a second source @NASASpaceflight X post Counts with a second source

  22. 2026-10-27 CONFIRMED note at P2 about S43 c-3a07c5d16bc0

    Ship 43 was lifted by the Pad 2 chopsticks with the landing rails deployed and moved back and forth, checking the rails and push rods after the previous night's SQD interface tests; Blobifie says this post-catch pusher test went much smoother than with Ship 42.

    @VickiCocks15 X post Counts with a second source @Blobifie X post Counts with a second source @FelixSchlang X post Counts with a second source

  23. 2026-10-27 UNCONFIRMED note at P2 about S43 c-c65eaa010472

    Blobifie says Ship 43 was moved to the middle of the Pad 2 chopsticks and lifted, a test simulating moving the ship forward after a catch so the stabilizer arms can engage.

    @Blobifie X post Counts with a second source

  24. 2026-10-26 CONFIRMED note at P2 about S43 c-eec7f163ae4b

    At Pad 2 the chopsticks lifted Ship 43 above its transport stand and up to the top of the tower, then lowered it to the height of the ship quick disconnect (SQD) arm, which connected to it: practice for post-catch safing operations.

    @Blobifie X post Counts with a second source @Blobifie X post Counts with a second source @NASASpaceflight X post Counts with a second source @FelixSchlang X post Counts with a second source @RGVaerialphotos X post Counts with a second source @VickiCocks15 X post Counts with a second source @Blobifie X post Counts with a second source

  25. 2026-10-26 CONFIRMED transport S43 to P2 c-0591c6539aff

    Ship 43 departed the production site and arrived at Pad 2 for chopstick testing.

    @RGVaerialphotos X post Counts with a second source @VickiCocks15 X post Counts with a second source @Blobifie X post Counts with a second source @LabPadre X post Counts with a second source

  26. 2026-10-26 UNCONFIRMED note at P2 c-f735a270f13d

    The City of Starbase Production to Pad road delay on Mon 26 Oct was extended from 10:00 to 14:00 CT to 10:00 to 15:00 CT, and the backup Highway 4 and beach closure for that day was revoked.

    @FelixSchlang X post Counts with a second source @FelixSchlang X post Counts with a second source @VickiCocks15 X post Counts with a second source

  27. 2026-10-26 UNCONFIRMED note at P2 about S43 c-a78aa194f37e

    Blobifie says Ship 43 went back onto its transport stand after the Pad 2 SQD connection test, and that the post-flight safing practice went much smoother than the same test with Ship 42.

    @Blobifie X post Counts with a second source

  28. 2026-10-26 CONFIRMED transport B22 from P2 to MB1 c-e2dea9fadb10

    Booster 22 was moved from Pad 2 back to Mega Bay 1 overnight after its static fire.

    @VickiCocks15 X post Counts with a second source @Blobifie X post Counts with a second source

  29. 2026-10-25 CONFIRMED note at P2 about B22 c-74a0e6a4213e

    Booster 22 was lifted off the Pad 2 launch mount to catch height at the top of the tower, then set on the booster transport ring for its trip back to Mega Bay 1 for final flight preparations.

    @RGVaerialphotos X post Counts with a second source @Blobifie X post Counts with a second source @NASASpaceflight X post Counts with a second source

  30. 2026-10-25 UNCONFIRMED note at P2 about B22 c-e02fc7cffe65

    After the static fire, the Pad 2 chopsticks descended and closed in around Booster 22, as stated by VickiCocks15.

    @VickiCocks15 X post Counts with a second source

  31. 2026-10-25 CONFIRMED note at P2 about B22 c-f3863dfdbddf

    SpaceX called the Booster 22 static fire for Flight 15 a full duration 33-engine static fire.

    @SpaceX X post Confirms alone @NASASpaceflight X post Counts with a second source

  32. 2026-10-25 UNCONFIRMED note at P2 c-8090fbd8f383

    Highway 4 and Boca Chica Beach were closed on 25 Oct from 7 AM to 7 PM ET for SpaceX spaceflight activities, with Monday 26 Oct as the backup, per FelixSchlang; Blobifie reported the road closed ahead of the static fire.

    @FelixSchlang X post Counts with a second source @Blobifie X post Counts with a second source

  33. 2026-10-25 UNCONFIRMED note at P2 about B22 c-e368e18c7435

    Booster 22 was detanked after its static fire on Pad 2.

    @Blobifie X post Counts with a second source

  34. 2026-10-25 UNCONFIRMED note at P2 c-6b8e42a0065e

    Ahead of the Booster 22 static fire, the Pad 2 chopsticks were opened and raised to launch position and the DSS was tested, as stated by VickiCocks15.

    @VickiCocks15 X post Counts with a second source

  35. 2026-10-25 CONFIRMED note at P2 about B22 c-2ed4b5250957

    The booster transport stand left the Pad 2 launch site ahead of the Booster 22 static fire; VickiCocks15 says it was moved to gate D1 for safety.

    @Blobifie X post Counts with a second source @LabPadre X post Counts with a second source @NASASpaceflight X post Counts with a second source @VickiCocks15 X post Counts with a second source

  36. 2026-10-25 CONFIRMED static-fire B22 at P2 c-7497db7affd7

    Booster 22 completed a static fire test on Pad 2 at Starbase. Blobifie reports the burn lasted more than 15 seconds.

    @NASASpaceflight X post Counts with a second source @LabPadre X post Counts with a second source @Blobifie X post Counts with a second source @FelixSchlang X post Counts with a second source @VickiCocks15 X post Counts with a second source @SpaceX X post Confirms alone

  37. 2026-10-24 CONFIRMED note at P2 about B22 c-27f38f636d95

    Booster 22 was lifted onto the Pad 2 orbital launch mount and lowered onto it on the afternoon of 24 Oct.

    @NASASpaceflight X post Counts with a second source @Blobifie X post Counts with a second source @Blobifie X post Counts with a second source @LabPadre X post Counts with a second source

  38. 2026-10-24 UNCONFIRMED note at P2 about B22 c-eab5f4451ac8

    With cranes down, Booster 22 on the mount, BQDs engaged and blast doors closed, VickiCocks15 says Pad 2 looks locked up ahead of testing planned for 25 Oct.

    @VickiCocks15 X post Counts with a second source

  39. 2026-10-24 UNCONFIRMED note at P2 c-58c6f7d92d91

    Littler Larry, the second SpaceX owned LR11000 crane at the launch site, was laid down during the Booster 22 lift on the morning of 24 Oct, following Maarvin, which was laid down on 23 Oct.

    @VickiCocks15 X post Counts with a second source

  40. 2026-10-24 CONFIRMED transport B22 from MB1 to P2 c-1ebcf26864d3

    Booster 22 was lifted onto a transport stand, left Mega Bay 1, drove Highway 4 and arrived at the launch site (Pad 2) on the morning of 24 Oct ahead of its static fire campaign.

    @Blobifie X post Counts with a second source @NASASpaceflight X post Counts with a second source @NASASpaceflight X post Counts with a second source @Blobifie X post Counts with a second source @VickiCocks15 X post Counts with a second source @FelixSchlang X post Counts with a second source

  41. 2026-10-23 CONFIRMED note at P2 c-87c7c1e990a3

    The SpaceX LR11000 crane at the Starbase launch site was lowered, which TrackingTheSB links to upcoming testing.

    @TrackingTheSB X post Confirms alone

  42. 2026-10-22 UNCONFIRMED note at P2 c-7c41daa05375

    Pad 2 completed another launch and landing deluge test.

    @Blobifie X post Counts with a second source

  43. 2026-10-22 UNCONFIRMED note at P2 c-2703ef43949c

    The booster quick disconnects (BQDs) at Pad 2 were tested with a few slow extend and retract moves, ending in a fast retract.

    @VickiCocks15 X post Counts with a second source

  44. 2026-10-22 UNCONFIRMED note at P2 c-26bf5a57aaaf

    In the same Pad 2 test thread, the hold down clamps were tested with a few individual retract and extend moves and a simultaneous retract, then one visible clamp extended and retracted alone; the deluge was then tested without the top deck.

    @VickiCocks15 X post Counts with a second source @VickiCocks15 X post Counts with a second source

  45. 2026-10-21 UNCONFIRMED note at P2 c-ba450eb5e0c5

    Booster quick disconnects (BQDs) at Starbase Pad 2 purging, which the post hopes is ahead of Booster 22 arriving soon.

    @NASASpaceflight X post Counts with a second source

  46. 2026-10-21 CONFIRMED note at P2 c-96b09ca5a132

    Pad 2 ran two water deluge tests about seven to eight minutes apart, one simulating a launch and one a catch, for the second day running. VickiCocks15 says the pressure looked higher than the day before.

    @VickiCocks15 X post Counts with a second source @RoughRidersShow X post Counts with a second source @FelixSchlang X post Counts with a second source @RGVaerialphotos X post Counts with a second source

  47. 2026-10-20 CONFIRMED note at P2 c-4548053919dc

    Chopstick testing at the top of the Pad 2 tower, with the deluge system activated during it; Blobifie reports both a launch and a landing deluge test.

    @VickiCocks15 X post Counts with a second source @VickiCocks15 X post Counts with a second source @Blobifie X post Counts with a second source @RoughRidersShow X post Counts with a second source

  48. 2026-10-19 UNCONFIRMED note at P2 c-2354811f6b72

    The launch mount service structure has been removed from Pad 2 and rolled back for storage near the D1 gate at the launch complex.

    @VickiCocks15 X post Counts with a second source

  49. 2026-10-18 UNCONFIRMED note at P2 c-351703f455c4

    TrackingTheSB weekly: late on 18 Oct the dancefloor service structure was removed from Pad 2 after post Flight 14 checkouts, then four full deluge tests including the top plate ran over 48 hours and the booster quick disconnects did a purge.

    @TrackingTheSB X post Confirms alone

  50. 2026-10-16 UNCONFIRMED note at P2 about pad2-chopsticks c-793f722ba51a

    Further chopstick testing at Pad 2.

    @VickiCocks15 X post Counts with a second source

  51. 2026-10-15 UNCONFIRMED note at P2 about pad2-chopsticks c-289f4e9f12d0

    Blobifie: SpaceX ran catch testing with the Pad 2 chopsticks at the top of the tower, and workers were seen celebrating at the top of the tower later in the day. NSF's Starbase summary of 15 Oct also shows the chopsticks run to the top of Tower 2 for high-speed tests.

    @Blobifie X post Counts with a second source @NASASpaceflight X post Counts with a second source @VickiCocks15 X post Counts with a second source

  52. 2026-10-14 UNCONFIRMED note at P2 c-917e300f41bf

    After damper work on 14 Oct (local), the Pad 2 chopsticks were raised and lowered a few times with checks in one pause; no arm swings were seen. The Deadline balcony at the base of Tower 2 received extra cladding the same day.

    @VickiCocks15 X post Counts with a second source @VickiCocks15 X post Counts with a second source

  53. 2026-10-08 UNCONFIRMED Flight 15 F15 NET 2026-11-08 at P2 c-3f2d98363b69

    CADENA advisory: Flight 15 from Starbase Pad 2 NET 8 Nov 2026; Flight 16 (Starlink 30-1), potentially LC-39A, NET 10 Dec 2026.

    @NASASpaceflight X post Counts with a second source @LabPadre X post Counts with a second source

  54. 2026-09-28 CONFIRMED Flight 14 F14 NET 2026-09-28 at P2 c-74fa6c3e2628

    Flight 14 lifted off from Starbase Pad 2 on 28 Sep 2026 at 7:48 a.m. CT.

    SpaceX Web page Confirms alone

  55. 2026-09-12 CONFIRMED note at P2 about pad2-sqd c-19665b5bfbaf

    Pad 2 SQD arm rotated in and connected to S42 at SQD height during catch rehearsal, a rehearsal of post-catch ship safing.

    @TrackingTheSB X post Confirms alone

  56. 2026-09-12 CONFIRMED identify hardware Pad 2 SQD arm c-30a10b89e0e6

    Identify the Pad 2 ship quick disconnect (SQD) arm as hardware used when S42 was lowered to SQD height and the SQD was connected during catch rehearsal.

    @TrackingTheSB X post Confirms alone

  57. 2026-09-12 CONFIRMED other S42 at P2 c-3c911339ea58

    Ship catch rehearsal at Pad 2: S42 was lifted to catch height and back down to SQD height, the SQD rotated in and connected, then S42 was rotated, flaps tucked, and lowered onto its transport stand.

    @TrackingTheSB X post Confirms alone

  58. 2026-09-10 CONFIRMED note at P2 about pad2-chopsticks c-bb7b05249641

    Pad 2 chopsticks held S42 deep in the arms and lifted it a few meters during catch rehearsal.

    @TrackingTheSB X post Confirms alone

  59. 2026-09-10 CONFIRMED identify hardware Pad 2 chopsticks c-86913ce720d0

    Identify the Pad 2 chopsticks as hardware used in Ship 42 catch rehearsals.

    @TrackingTheSB X post Confirms alone

  60. 2026-09-10 CONFIRMED note at P2 c-509afe456ce6

    Pad 2 OLM ran a further deluge test.

    @TrackingTheSB X post Confirms alone

  61. 2026-09-10 CONFIRMED other S42 at P2 c-5e1953d56a83

    Ship catch rehearsal at Pad 2: S42 was placed deep in the chopsticks and lifted a few meters, then the chopstick pushers moved it to the stabilizer engagement position and the stabilizers were engaged.

    @TrackingTheSB X post Confirms alone

  62. 2026-09-08 CONFIRMED note at P2 c-42cd710b9851

    Pad 2 OLM ran a full launch-to-catch deluge operation.

    @TrackingTheSB X post Confirms alone

  63. 2026-07-24 CONFIRMED Flight 13 F13 NET 2026-07-24 at P2 c-7bf904a1def2

    Flight 13 lifted off from Starbase Pad 2 on 24 Jul 2026 at 5:51 p.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  64. 2026-05-22 CONFIRMED Flight 12 F12 NET 2026-05-22 at P2 c-3cf9efbc11f3

    Flight 12 lifted off from Starbase Pad 2 on 22 May 2026 at 5:30 p.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

Flights

7 schedules that name this pad. A NET is not a liftoff.

  1. Flight 12 NET 2026-05-22 2026-05-22 CONFIRMED Flight 12 F12 NET 2026-05-22 at P2 c-3cf9efbc11f3

    Flight 12 lifted off from Starbase Pad 2 on 22 May 2026 at 5:30 p.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  2. Flight 13 NET 2026-07-24 2026-07-24 CONFIRMED Flight 13 F13 NET 2026-07-24 at P2 c-7bf904a1def2

    Flight 13 lifted off from Starbase Pad 2 on 24 Jul 2026 at 5:51 p.m. CT.

    SpaceX Web page Confirms alone SpaceX Web page Confirms alone

  3. Flight 14 NET 2026-09-28 2026-09-28 CONFIRMED Flight 14 F14 NET 2026-09-28 at P2 c-74fa6c3e2628

    Flight 14 lifted off from Starbase Pad 2 on 28 Sep 2026 at 7:48 a.m. CT.

    SpaceX Web page Confirms alone

  4. Flight 15 NET 2026-11-08 2026-10-08 UNCONFIRMED Flight 15 F15 NET 2026-11-08 at P2 c-3f2d98363b69

    CADENA advisory: Flight 15 from Starbase Pad 2 NET 8 Nov 2026; Flight 16 (Starlink 30-1), potentially LC-39A, NET 10 Dec 2026.

    @NASASpaceflight X post Counts with a second source @LabPadre X post Counts with a second source

  5. Flight 15 NET 2026-11-12 2026-10-29 UNCONFIRMED Flight 15 F15 NET 2026-11-12 at P2 c-f99b81d052de

    Flight 15 (Booster 22 and Ship 42) moved 4 days to NET 12 Nov 2026 per CADENA and a new FAA planning slide, which earlier listed 8 Nov. The FAA slide is a planning date, not a SpaceX date, and no Flight 15 launch licence is public yet.

    @LabPadre X post Counts with a second source @FelixSchlang X post Counts with a second source @lewisknaggs42 X post Counts with a second source @NASASpaceflight X post Counts with a second source @StarshipGazer X post Counts with a second source

  6. Flight 15 NET 2026-11-13 2026-11-05 UNCONFIRMED Flight 15 F15 NET 2026-11-13 at P2 c-b2adfdd0de4b

    Flight 15 moved one day to NET 13 Nov 2026 per the Nov 5 CADENA FAA planning slide (was 12 Nov). LabPadre, FelixSchlang and lewisknaggs42 all cite the slide; LabPadre notes these are tentative planning dates, not NOTAMs. No Flight 15 launch licence is public yet.

    @LabPadre X post Counts with a second source @FelixSchlang X post Counts with a second source @lewisknaggs42 X post Counts with a second source

  7. Flight 15 NET 2026-11-13 2026-11-07 CONFIRMED F15 NET 2026-11-13 at P2 c-638524a443e2

    SpaceX says Flight 15 is preparing to launch as soon as Friday 13 Nov 2026, pending regulatory approval, from Starbase. NSF says SpaceX tested the launch site systems ahead of rolling both vehicles to Pad 2.

    SpaceX Web page Confirms alone @SpaceX X post Confirms alone @NASASpaceflight X post Counts with a second source

Florida

LC-39A 39A

Starship launch tower at Kennedy Space Center

Ground systems

One mark per claim whose effect at is this pad, or whose about names hardware the ledger places here. The earliest word in the summary picks the lane. Words that start together keep the longer one. A summary with none of them is Other. Filled marks are confirmed. Hollow marks are unconfirmed, and the table keeps the UNCONFIRMED stamp.

LC-39A ground systems, 3 Jul to 25 OctLaunch mount / legsChopsticks / towerDeluge / water tanksBQD / SQDFlame deflectorTank farm / propellantOther3 Jul10 Jul17 Jul24 Jul31 Jul7 Aug14 Aug21 Aug28 Aug4 Sept11 Sept18 Sept25 Sept2 Oct9 Oct16 Oct23 Oct2026-07-03 Chopsticks / tower UNCONFIRMED: As of early July 2026, NSF reports LC-39A chopsticks are reeved so they can move on the tower, and ridge-cap and bucket deluge testing has begun.2026-09-03 Chopsticks / tower: Artemis III crew visit the Starship launch tower at LC-39A.2026-09-12 Chopsticks / tower UNCONFIRMED: NSF (25 Oct): SpaceX has begun activation testing of all LC-39A pad systems, with the tower vent first activated on 12 Sep, which helped fully purge and test the ship-side systems.2026-10-12 Chopsticks / tower UNCONFIRMED: NSF (25 Oct): on 12 Oct SpaceX installed a new reinforced roof on the LC-39A tower to protect the top of the tower during ship catches; NSF says all four towers SpaceX has stacked now have reinforced roofs.2026-10-25 Tank farm / propellant UNCONFIRMED: NSF (25 Oct): SpaceX has added two more liquid methane (LCH4) storage tanks at LC-39A, completing that side of the tank farm; once hooked in, NSF puts LC-39A at nearly 5,000 metric tons of LCH4, about 3.8 stacks' worth. More liquid nitrogen capacity was also added to the deluge farm.2026-10-25 Other UNCONFIRMED: TrackingTheSB weekly: LC-39A is in final testing ahead of its first vehicle, set for Flight 16; the presumed Flight 16 pairing is Booster 23 and Ship 43.
DateLaneSummaryClaim
2026-07-03Chopsticks / towerAs of early July 2026, NSF reports LC-39A chopsticks are reeved so they can move on the tower, and ridge-cap and bucket deluge testing has begun.c-5eec7a5ff274 UNCONFIRMED
2026-09-03Chopsticks / towerArtemis III crew visit the Starship launch tower at LC-39A.c-915de77b5552
2026-09-12Chopsticks / towerNSF (25 Oct): SpaceX has begun activation testing of all LC-39A pad systems, with the tower vent first activated on 12 Sep, which helped fully purge and test the ship-side systems.c-5f11b92cd2b5 UNCONFIRMED
2026-10-12Chopsticks / towerNSF (25 Oct): on 12 Oct SpaceX installed a new reinforced roof on the LC-39A tower to protect the top of the tower during ship catches; NSF says all four towers SpaceX has stacked now have reinforced roofs.c-d59a8070314c UNCONFIRMED
2026-10-25Tank farm / propellantNSF (25 Oct): SpaceX has added two more liquid methane (LCH4) storage tanks at LC-39A, completing that side of the tank farm; once hooked in, NSF puts LC-39A at nearly 5,000 metric tons of LCH4, about 3.8 stacks' worth. More liquid nitrogen capacity was also added to the deluge farm.c-03f9d2061ae3 UNCONFIRMED
2026-10-25OtherTrackingTheSB weekly: LC-39A is in final testing ahead of its first vehicle, set for Flight 16; the presumed Flight 16 pairing is Booster 23 and Ship 43.c-ac08e1d70645 UNCONFIRMED
Launch mount / legs
orbital launch mount, launch mount, mount legs, mount leg, olm
Chopsticks / tower
chopsticks, chopstick, towers, tower
Deluge / water tanks
deluge, water tanks, water tank
BQD / SQD
quick disconnects, quick disconnect, quick-disconnects, quick-disconnect, bqds, bqd, sqds, sqd
Flame deflector
flame deflector, deflector, flame trench, flame bucket
Tank farm / propellant
tank farm, propellant
Other
no word from the lanes above

Components

0 pieces from the hardware register. Now at is the last confirmed place a source stated, or an unconfirmed place stamped as such when nothing confirms one. A newer unconfirmed place sits beside it as a candidate.

No hardware in the register is tied to this pad.

Activity

7 claims, newest first. An effect that names this pad, or a claim about hardware tied to it. Unconfirmed claims stay stamped.

  1. 2026-10-25 UNCONFIRMED note at 39A about F16 c-ac08e1d70645

    TrackingTheSB weekly: LC-39A is in final testing ahead of its first vehicle, set for Flight 16; the presumed Flight 16 pairing is Booster 23 and Ship 43.

    @TrackingTheSB X post Confirms alone

  2. 2026-10-25 UNCONFIRMED note at 39A c-03f9d2061ae3

    NSF (25 Oct): SpaceX has added two more liquid methane (LCH4) storage tanks at LC-39A, completing that side of the tank farm; once hooked in, NSF puts LC-39A at nearly 5,000 metric tons of LCH4, about 3.8 stacks' worth. More liquid nitrogen capacity was also added to the deluge farm.

    NASASpaceflight Web page Counts with a second source

  3. 2026-10-12 UNCONFIRMED note at 39A c-d59a8070314c

    NSF (25 Oct): on 12 Oct SpaceX installed a new reinforced roof on the LC-39A tower to protect the top of the tower during ship catches; NSF says all four towers SpaceX has stacked now have reinforced roofs.

    NASASpaceflight Web page Counts with a second source

  4. 2026-10-08 UNCONFIRMED Flight 16 (Starlink 30-1) F16 NET 2026-12-10 at 39A c-7dc009ede861

    CADENA advisory: Flight 15 from Starbase Pad 2 NET 8 Nov 2026; Flight 16 (Starlink 30-1), potentially LC-39A, NET 10 Dec 2026.

    @NASASpaceflight X post Counts with a second source @LabPadre X post Counts with a second source

  5. 2026-09-12 UNCONFIRMED note at 39A c-5f11b92cd2b5

    NSF (25 Oct): SpaceX has begun activation testing of all LC-39A pad systems, with the tower vent first activated on 12 Sep, which helped fully purge and test the ship-side systems.

    NASASpaceflight Web page Counts with a second source

  6. 2026-09-03 CONFIRMED note at 39A c-915de77b5552

    Artemis III crew visit the Starship launch tower at LC-39A.

    @LabPadre X post Counts with a second source

  7. 2026-07-03 UNCONFIRMED note at 39A c-5eec7a5ff274

    As of early July 2026, NSF reports LC-39A chopsticks are reeved so they can move on the tower, and ridge-cap and bucket deluge testing has begun.

    NASASpaceflight Web page Counts with a second source

Flights

1 schedule that name this pad. A NET is not a liftoff.

  1. Flight 16 (Starlink 30-1) NET 2026-12-10 2026-10-08 UNCONFIRMED Flight 16 (Starlink 30-1) F16 NET 2026-12-10 at 39A c-7dc009ede861

    CADENA advisory: Flight 15 from Starbase Pad 2 NET 8 Nov 2026; Flight 16 (Starlink 30-1), potentially LC-39A, NET 10 Dec 2026.

    @NASASpaceflight X post Counts with a second source @LabPadre X post Counts with a second source

Florida

SLC-37 37

Planned Starship launch complex, Cape Canaveral

Ground systems

One mark per claim whose effect at is this pad, or whose about names hardware the ledger places here. The earliest word in the summary picks the lane. Words that start together keep the longer one. A summary with none of them is Other. Filled marks are confirmed. Hollow marks are unconfirmed, and the table keeps the UNCONFIRMED stamp.

DateLaneSummaryClaim
2026-07-03Chopsticks / towerAs of early July 2026, NSF reports the SLC-37A tower had four of nine modules stacked, the flame trench was fully excavated, and rebar for the trench floor was underway.c-d33519168004 UNCONFIRMED
2026-09-23Tank farm / propellantNASA's HLS IAC 2026 SpaceX milestone chart, running Q4 2026 to Q1 2028, lists 2nd Pad at Cape (LC37) Complete among its launch infrastructure milestones, after the propellant transfer demo.c-3893d1509522
2026-09-29OtherFAA announced a Notice of Intent to prepare a Supplemental EIS for Starship-Super Heavy operations at SLC-37 at Cape Canaveral Space Force Station. The public comment period ended 14 Oct 2026.c-b642205858b7
2026-10-14OtherFAA public comment period for the SLC-37 Supplemental EIS Notice of Intent ended on 14 Oct 2026. Comments will be considered in the Draft SEIS.c-b66a0cfce774
Launch mount / legs
orbital launch mount, launch mount, mount legs, mount leg, olm
Chopsticks / tower
chopsticks, chopstick, towers, tower
Deluge / water tanks
deluge, water tanks, water tank
BQD / SQD
quick disconnects, quick disconnect, quick-disconnects, quick-disconnect, bqds, bqd, sqds, sqd
Flame deflector
flame deflector, deflector, flame trench, flame bucket
Tank farm / propellant
tank farm, propellant
Other
no word from the lanes above

Components

0 pieces from the hardware register. Now at is the last confirmed place a source stated, or an unconfirmed place stamped as such when nothing confirms one. A newer unconfirmed place sits beside it as a candidate.

No hardware in the register is tied to this pad.

Activity

4 claims, newest first. An effect that names this pad, or a claim about hardware tied to it. Unconfirmed claims stay stamped.

  1. 2026-10-14 CONFIRMED note at 37 c-b66a0cfce774

    FAA public comment period for the SLC-37 Supplemental EIS Notice of Intent ended on 14 Oct 2026. Comments will be considered in the Draft SEIS.

    FAA Web page Confirms alone

  2. 2026-09-29 CONFIRMED note at 37 c-b642205858b7

    FAA announced a Notice of Intent to prepare a Supplemental EIS for Starship-Super Heavy operations at SLC-37 at Cape Canaveral Space Force Station. The public comment period ended 14 Oct 2026.

    FAA Web page Confirms alone

  3. 2026-09-23 CONFIRMED note at 37 c-3893d1509522

    NASA's HLS IAC 2026 SpaceX milestone chart, running Q4 2026 to Q1 2028, lists 2nd Pad at Cape (LC37) Complete among its launch infrastructure milestones, after the propellant transfer demo.

    NASA Web page Confirms alone

  4. 2026-07-03 UNCONFIRMED note at 37 c-d33519168004

    As of early July 2026, NSF reports the SLC-37A tower had four of nine modules stacked, the flame trench was fully excavated, and rebar for the trench floor was underway.

    NASASpaceflight Web page Counts with a second source

Flights

0 schedules that name this pad. A NET is not a liftoff.

No schedule names this pad.