Nerdy, sourced Starship tracking at every site

Claimstrip

06:14 CST at Starbase

Starbase

Sanchez lot SAN

Ground hardware and pad component assembly

Sanchez lot SANGigabay bridge crane trolleys (two)UNCONFIRMEDPad 1 orbital launch mount (rebuild)UNCONFIRMED Starbase Pad 1Pad 1 SQD arm (rebuild)

Claims

  1. happened

    2026-10-27 UNCONFIRMED note at SAN

    VickiCocks15 says a crane at Sanchez lifted one of the top deck plates for the new Pad 1 launch mount, which she believes is the 3rd of 4 sections.

    @VickiCocks15 X post Counts with a second source

  2. happened

    2026-10-22 UNCONFIRMED note at SAN about gigabay-bridge-crane-trolleys

    Two Gigabay bridge crane trolleys were redirected to Sanchez for storage until needed for installation.

    @VickiCocks15 X post Counts with a second source

  3. happened

    2026-10-18 UNCONFIRMED note at SAN

    In the Sanchez lot, the large LOX and CH4 valve skids for the Pad 1 rebuild are being pre-installed onto two large frames. The post says this likely means they can be installed as complete units driven in on SPMTs; for Pad 2 this equipment was brought in and installed separately.

    @AshleyKillip X post Counts with a second source

  4. departed

    2026-10-14 transport 4PL (four point lifter) from SAN to MB2

    The 4PL used for ship lifts moved from Sanchez into Mega Bay 2 and hoisted from its stand.

    @VickiCocks15 X post Counts with a second source

  5. happened

    2026-10-11 note at SAN about pad1-sqd

    Pad 1 SQD arm under construction in the Sanchez lot; TrackingTheSB says work on it continued steadily through the week of 5 Oct.

    @TrackingTheSB X post Confirms alone @RGVaerialphotos X post Counts with a second source

  6. happened

    2026-10-11 note at SAN about pad1-olm

    New Pad 1 orbital launch mount under construction in the Sanchez lot; TrackingTheSB says work on it continued steadily through the week of 5 Oct.

    @TrackingTheSB X post Confirms alone @RGVaerialphotos X post Counts with a second source

  7. happened

    2026-10-11 note at SAN about pad1-flame-deflector

    Pad 1 flame deflector under construction in the Sanchez lot; TrackingTheSB says work on it continued steadily through the week of 5 Oct.

    @TrackingTheSB X post Confirms alone @RGVaerialphotos X post Counts with a second source

  8. arrived

    2026-10-10 transport S40 from PoB to SAN

    Ship 40 offloaded from Forte and rolled overnight from the Port of Brownsville to the production site.

    @RGVaerialphotos X post Counts with a second source @TrackingTheSB X post Confirms alone